Automated case summary
What the court decided
The issue at stake in this case was whether David Ingle's application for interlocutory review of a trial court order was timely, given that the trial court had certified its order for immediate review only 41 days after entry. The key facts include that the underlying order was not served on parties until March 26, 2026, and that the ten-day deadline for certification began to run upon the "entry" of the order. The Court of Appeals held that Ingle's application was dismissed because the trial court's certificate of immediate review was entered 41 days after entry of the underlying order, exceeding the required ten-day period.